Phase V Construction Projects
The Edward C. Little Water Recycling Facility in El Segundo is gearing up for its fifth expansion since initial construction in 1995. Phase V will double the plant's production of recycled water.
December 15, 2011 Update:
GRAVITY BELT THICKENER


The GRAVITY BELT THICKENER building went up in one day using the tilt-up method. The new building will house equipment to dewater sludge and obtain a higher solid concentrate (ie. create efficiencies in operations) and comes with an odor control system.
MITIGATED NEGATIVE DECLARATION
To view a downloadable PDF version of the Mitigated Negative Declaration (5MB), click here:
Edward C. Little Water Recycling Facility Phase V Expansion Project Initial Study/Mitigated Negative Declaration
To view the Capital Implementation Master Plan, click here.
BRINE PERMIT PACKAGE
Here you will find correspondence from the Los Angeles Regional Water Quality Control Board (Regional Water Board), regarding the renewal of Wastewater Discharge Requirements (WDR) and National Pollutant Discharge Elimination System (NPDES) permit for the Edward C. Little Water Recycling Plant owned by the West Basin Municipal Water District. Public Comments may be submitted to the LARWQCB on or before December 8, 2011 at: c/o Don Tsai, LARWQCB, 320 West Fourth Street, Suite 200, Los Angeles, 90013
For more information, please contact Uzi Daniel at uzid@westbasin.org. Posting date: October 27, 2011.
Cover letter for Tentative Permit
Instructions for Posting Notice
Public Notice
Tentative Brine R4-2012
Attachment G - Stormwater pollution prevention requirements
Attachment H - Biosolids and Sludge Management
Tentative Brine R4-2012